Esquimalt Urgent Primary Care
Vancouver Island Health Authority
Architect: | Continuum Architecture |
Role: | Mechanical Consultant |
Duration: | Feb 2021 - Jan 2022 |
Budget: | $1,650,000 |
Area: | 312 sqm [3,360 sqft] |
Discipline: | Plumbing - HVAC |
Contractor: | Century Group Constructors |
The project was the design and construction services for a new Primary Care Clinic in Esquimalt, BC. The space consists of a large public waiting area, multiple exam & consultation rooms, and staff/administrative spaces. The clinic was constructed in an existing commercial retail facility and utilized the following systems:
- New Variable Refrigerant Flow system to provide space heating and cooling with ceiling mounted Fan Coil Units.
- New Domestic Hot Water system with mixing valve and intelligent control system to prevent potential scolding.
The project had a compressed design timeframe to work with the tight construction schedule to allow successful opening of the facility in May 2022.